Tata Powers 3000 Cr. Solar Manufacturing Facility Will Be Operational In 2023

Tata Powers 3000 Cr. Solar Manufacturing Facility Will Be Operational By Year End

Tata Power signed an agreement with the Tamil Nadu government in July 2022 to spend Rs 3,000 crore in the state’s Tirunelveli district to establish a new factory to produce solar cells and modules. According to Memorandum of Understanding (MoU) Tata Power has to build a greenfield 4GW solar cell and 4GW solar module manufacturing factory in the southern state.

Tata Power

The construction work is going on in full swing. The equipment to set up the unit have already been ordered. The aim is to make the plant operational by December-end of this year.

The business expects the module production to be operational by August-September, with module deliveries beginning in September. The business is well on its way to completing the cell lines, which will likewise be available by the end of the year.

Tata Power Renewable Energy Ltd (TPREL), a Tata Power subsidiary, obtained a letter of award (LoA) from Tata Power Delhi Distribution Ltd (TPDDL) in December 2022 to establish the wind and solar hybrid power project in Karnataka. The business is awaiting regulatory certification and permits from the regulatory commission for the 225 MW hybrid project in Karnataka.